5. Reconstruction / adaptation of real estate |
19,3% of respondents claimed they were looking for reconstruction
permits or changing the purpose, by reconstruction, of the real
estate; the so-called adaptation permit, but only
54,35% of that number actually had the permits all cleared.
Average time for:
getting
all the permits for reconstruction or adaptation is 118
days
reconstruction
is 118 days (122 worker-days)
getting
permits for reconstruction or changing is 77 days (34
worker-days)
connection
of: water, sewer, electricity, etc: 18 days (211
worker-days)
the
work (reconstruction and networks) is 333 worker-days
Average cost for getting permits for reconstruction/adaptation
of real estate:
|
Permit for reconstruction/correction: |
|
cost of registering: |
125 €
|
|
official fees: |
175 €
|
|
penalties: |
100 €
|
|
bribe: |
183 €
|
|
total cost: |
210 €
|
|
Approval of the reconstruction plan: |
|
cost of registering: |
0 €
|
|
official fees: |
0 €
|
|
penalties: |
0 €
|
|
bribe: |
0 €
|
|
total cost: |
0 €
|
|
Reconstruction process: |
|
cost of registering: |
0 €
|
|
official fees: |
40 €
|
|
penalties: |
0 €
|
|
bribe: |
6,000 €
|
|
total cost: |
6,040 €
|
|
Connection to local utilities: |
|
cost of registering: |
141 €
|
|
official fees: |
1,015 €
|
|
penalties: |
0 €
|
|
bribe: |
25 €
|
|
total cost: |
583 €
|
|
Technical control and approval of the building: |
|
cost of registering: |
105 €
|
|
official fees: |
67 €
|
|
penalties: |
50 €
|
|
bribe: |
391 €
|
|
total cost: |
206 €
|
One amount for all permits: 650 €
|
|