4. Construction of new buildings |
One out of five respondents constructed a new building; 64,29%
of that number had permits and authorizations while 35,71% were
building without permits.
Average time for:
|
obtaining all the permits: |
326 days |
|
building objects: |
400 days (524 worker-days of employees) |
|
obtaining legitimate right for using the land: |
76 days (111 worker-days) |
|
obtaining the construction permit: |
95 days (24 worker-days) |
|
obtaining right for using the land and construction permit: |
176 days (42,75% of the complete time needed for the construction
process) |
|
getting all permits to start building: |
35 worker-days (almost two months of working time of an
employee) |
Average total costs for using land and building permits:
|
Legitimate right for using the land permit: |
1,030 € |
|
Construction permit: |
762.40 € |
|
Approval of the project: |
885.25 € |
|
Building process: |
75 € |
|
Connections: water, sewer, electricity, etc: |
880 € |
|
Technical control and approval of the building: |
250 € |
|
One amount for all permits*: |
3,893 € |
*service of the agent or broker, without ability or option to
see an itemized bill for each cost.
|
|