Tunnel construction proceeding as planned
NIKSIC - In spite of initial problems with the unstable terrain, the construction of a road tunnel in Sozina is proceeding as planned on the southern side.
So far, 750 m of the tunnel have been dug out on that side, an average of 60-70 m monthly.
|
|
|
|
|